[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108418":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108418,783,1,"单选题","根据批准的初步设计安排单位工程的开竣工日期，属于建设工程进度计划体系中（ ）内容。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程项目前期工作计划",false,{"key":16,"text":17,"correct":14},"B","单位工程施工进度计划",{"key":19,"text":20,"correct":21},"C","工程项目总进度计划",true,{"key":23,"text":24,"correct":14},"D","工程项目年度进度计划","考点:建设单位的计划系统。工程项目总进度计划是根据初步设计中确定的建设工期和工艺流程，具体安排单位工程的开工日期和竣工日期。参见教材P7",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]