[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108417":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108417,783,1,"单选题","（ ）是依据工程项目可行性研究报告、工程项目前期工作计划和工程项目建设总进度计划编制的。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理设计阶段进度计划",false,{"key":16,"text":17,"correct":18},"B","监理总进度计划",true,{"key":20,"text":21,"correct":14},"C","监理施工阶段进度计划",{"key":23,"text":24,"correct":14},"D","监理年度进度计划","考点:监理单位的计划系统。监理总进度计划是依据工程项目可行性研究报告、工程项目前期工作计划和工程项目建设总进度计划编制的。参见教材P9",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]