[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108416":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108416,783,1,"单选题","施工单位的计划系统中，施工准备的工作内容通常包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","技术准备",true,{"key":16,"text":17,"correct":18},"B","确定进场人员",false,{"key":20,"text":21,"correct":18},"C","确定项目经理",{"key":23,"text":24,"correct":18},"D","确定供货单位","考点:施工单位的计划系统。施工准备工作内容通常包括：技术准备、物资准备、劳动组织准备、施工现场准备、施工场外准备。参见教材P12",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]