[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108415":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108415,783,1,"单选题","下列属于采用横道图表示工程进度计划的主要特点的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","能够明确地反映出各项工作之间错综复杂的相互关系",false,{"key":16,"text":17,"correct":14},"B","能够明确表达地反映出影响工期的关键工作",{"key":19,"text":20,"correct":21},"C","易于编制和便于理解",true,{"key":23,"text":24,"correct":14},"D","能方便地利用计算机进行计算和优化","考点:建设工程进度计划的表示方法。横道图优点：形象直观地表达每一个工作的开始、结束和持续时间，并且易于编制和便于理解。缺点：不能明确地反映出各项工作之间错综复杂的相互关系；不能明确地反映出影响工期的关键工作和关键线路；不能反映出工作所具有的机动时间；不能反映工程费用与工期之间的关系。参见教材P13",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]