[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108414":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108414,783,1,"单选题","与横道图表示的进度计划相比，网络计划的主要特征是能够明确表达（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","单位时间内的资源需求量",false,{"key":16,"text":17,"correct":18},"B","各项工作之间的逻辑关系",true,{"key":20,"text":21,"correct":14},"C","各项工作的持续时间",{"key":23,"text":24,"correct":14},"D","各项工作之间的搭接时间","考点:建设工程进度计划的表示方法。网络计划特点：（1）网络计划能够明确表达各项工作之间的逻辑关系；（2）通过网络计划时间参数的计算，可以找出关键线路和关键工作；（3）通过网络计划时间参数的计算，可以明确各项工作的机动时间；（4）网络计划可以利用电子计算机进行计算、优化和调整。参见教材P15",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]