[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108413":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108413,783,1,"单选题","网络计划的目标由工程项目的目标所决定，其中以限定的工期寻求最低成本或寻求最低成本时的工期安排属于（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","时间目标",false,{"key":16,"text":17,"correct":14},"B","时间-资源目标",{"key":19,"text":20,"correct":21},"C","时间-成本目标",true,{"key":23,"text":24,"correct":14},"D","时间-投资目标","考点:建设工程进度计划的编制程序。时间-成本目标是指以限定的工期寻求最低成本或寻求最低成本时的工期安排。参见教材P17",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]