[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108411":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108411,783,1,"单选题","在工程建设过程中，属于影响工程进度的组织管理因素是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","不合理的施工方案",false,{"key":16,"text":17,"correct":14},"B","不明的水文气象条件",{"key":19,"text":20,"correct":21},"C","向有关部门提出各种申请审批手续的延误",true,{"key":23,"text":24,"correct":14},"D","设计内容不完善，规范应用不恰当","考点:影响进度的因素分析。选项A属于施工技术因素，选项B属于自然环境因素，选项D属于勘察设计因素。参见教材P2。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]