[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108408":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108408,783,1,"单选题","在建设工程进度控制计划体系中，不属于设计单位计划系统的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","设计总进度计划",false,{"key":16,"text":17,"correct":14},"B","阶段性设计进度计划",{"key":19,"text":20,"correct":14},"C","设计作业进度计划",{"key":22,"text":23,"correct":24},"D","年度建设资金计划",true,"考点:设计单位的计划系统。设计单位的计划系统包括：设计总进度计划、阶段性设计进度计划和设计作业进度计划。参见教材P10",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]