[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108407":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108407,783,1,"单选题","监理单位接受建设单位委托实施工程项目全过程监理时，需要（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","编制设计和施工总进度计划",false,{"key":16,"text":17,"correct":18},"B","审查设计单位和施工单位提交的进度计划",true,{"key":20,"text":21,"correct":14},"C","编制单位工程施工进度计划",{"key":23,"text":24,"correct":14},"D","编制详细的出图计划并控制其执行","考点:进度控制的措施和主要任务。在设计阶段和施工阶段，监理工程师不仅要审查设计单位和施工单位提交的进度计划，更要编制监理进度计划，以确保进度控制目标的实现。参见教材P3",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]