[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108405":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108405,783,1,"单选题","建设工程施工阶段进度控制的主要任务是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","调查和分析工程环境及施工现场条件",false,{"key":16,"text":17,"correct":18},"B","编制单位工程施工进度计划",true,{"key":20,"text":21,"correct":14},"C","进行工期目标和进度控制决策",{"key":23,"text":24,"correct":14},"D","编制年度竣工投产支付使用费用","考点:进度控制的措施和主要任务。施工阶段进度控制的主要任务包括：编制施工总进度计划，并控制其执行；编制单位工程施工进度计划，并控制其执行；编制年、季、月实施计划，并控制其执行。参见教材P3",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]