[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108404":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108404,783,1,"单选题","为确保建设工程进度控制目标的实现，项目监理机构可采取的技术措施是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建立工程进度信息沟通网络",false,{"key":16,"text":17,"correct":18},"B","审查承包商提交的进度计划",true,{"key":20,"text":21,"correct":14},"C","及时办理工程进度款支付手续",{"key":23,"text":24,"correct":14},"D","建立实际进度检查分析制度","考点:进度控制的措施和主要任务。进度控制的技术措施主要包括：（1）审查承包商提交的进度计划，使承包商能在合理的状态下施工；（2）编制进度控制工作细则，指导监理人员实施进度控制；（3）采用网络计划技术及其他科学适用的计划方法，并结合电子计算机的应用，对建设工程进度实施动态控制。参见教材P3。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]