[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108401":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108401,783,1,"单选题","整个项目划分成多少计划层，应根据项目的（ ）而定。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","规模和特点",true,{"key":16,"text":17,"correct":18},"B","质量和投资",false,{"key":20,"text":21,"correct":18},"C","质量和进度",{"key":23,"text":24,"correct":18},"D","进度和特点","考点:建设项目总进度目标的论证。整个项目划分成多少计划层，应根据项目的规模和特点而定。参见教材P5。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]