[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108399":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108399,783,1,"单选题","建设工程进度计划的表示方法中，（ ）虽不能明确地反映出影响工期的关键工作和关键线路，但是由于其形象、直观，且易于编制和理解，被广泛应用。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","横道图",true,{"key":16,"text":17,"correct":18},"B","时标网络计划",false,{"key":20,"text":21,"correct":18},"C","搭接网络计划",{"key":23,"text":24,"correct":18},"D","多级网络计划","考点:建设工程进度计划的表示方法。横道图也称甘特图，由于其形象、直观，且易于编制和理解，因而长期以来广泛应用于建设工程进度控制之中。参见教材P13。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]