[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108398":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108398,783,1,"单选题","横道计划作为控制建设工程进度的方法之一，其局限性是不能（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","反映出建设工程实施过程中劳动力的需求量",false,{"key":16,"text":17,"correct":18},"B","明确反映出各项工作之间错综复杂的相互关系",true,{"key":20,"text":21,"correct":14},"C","反映出建设工程实施过程中材料的需求量",{"key":23,"text":24,"correct":14},"D","直观地反映出建设工程的施工期限","考点:建设工程进度计划的表示方法。横道计划存在的缺点：（1）不能明确地反映出各项工作之间错综复杂的相互关系；（2）不能明确地反映出影响工期的关键工作和关键线路；（3）不能反映出工作所具有的机动时间；（4）不能反映工程费用与工期之间的关系。参见教材P13",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]