[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108394":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108394,783,1,"单选题","建设单位编制的进度计划在建设工程进度控制计划体系中不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程项目建设总进度计划",false,{"key":16,"text":17,"correct":14},"B","工程项目前期工作计划",{"key":19,"text":20,"correct":21},"C","施工图进度计划",true,{"key":23,"text":24,"correct":14},"D","工程项目年度计划","考点:建设单位的计划系统。建设单位编制的进度计划包括工程项目前期工作计划、工程项目建设总进度计划和工程项目年度计划。参见教材P6",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]