[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108390":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108390,783,1,"单选题","某建设项目工程总承包方为了协助业主进行项目总进度目标的控制，对项目的总进度目标进行了分析和论证，编制了项目总进度纲要。在总进度目标论证时做了以下工作： ①调查研究； ②编制总进度计划； ③编制各层进度计划； ④项目结构分析； ⑤项目的工作编码； ⑥进度计划系统的结构分析； 则，建设项目工程总承包方进行总进度目标论证时，其工作顺序应为（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","①一②一③一⑥一④一⑤",false,{"key":16,"text":17,"correct":14},"B","①一③一②一⑥一④一⑤",{"key":19,"text":20,"correct":14},"C","①一③一②一⑤一④一⑥",{"key":22,"text":23,"correct":24},"D","①一④一⑥一⑤一③一②",true,"考点:建设项目总进度目标的论证。参见教材P4。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]