[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108387":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108387,783,1,"单选题","（）是一个由若干个处于不同层次且相互间有关联的网络计划组成的系统。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","搭接网络计划",false,{"key":16,"text":17,"correct":14},"B","时标网络计划",{"key":19,"text":20,"correct":21},"C","多级网络计划",true,{"key":23,"text":24,"correct":14},"D","横道图计划","考点:建设工程进度计划的表示方法。多级网络计划是一个由若干个处于不同层次且相互间有关联的网络计划组成的系统，其主要适用于大、中型工程建设项目，用来解决工程进度中的综合平衡问题。参见教材P14。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]