[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108385":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108385,783,1,"单选题","建设工程进度计划的编制一般包含以下四个阶段：①计划准备阶段、②计算时间参数及确定关键线路阶段、③网络计划优化阶段、④绘制网络图阶段，其正确程序应该是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","①②③④",false,{"key":16,"text":17,"correct":14},"B","①③②④",{"key":19,"text":20,"correct":21},"C","①④②③",true,{"key":23,"text":24,"correct":14},"D","①②④③","考点:建设工程进度计划的编制程序。参见教材P16。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]