[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108384":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108384,783,1,"单选题","工程项目建设总进度计划是根据（）对工程项目从开始至竣工投产的全过程的统一部署。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","初步设计",true,{"key":16,"text":17,"correct":18},"B","项目评估报告",false,{"key":20,"text":21,"correct":18},"C","可行性研究报告",{"key":23,"text":24,"correct":18},"D","施工图预算","考点:建设工程进度控制计划体系。工程项目建设总进度计划是指初步设计被批准后，在编报工程项目年度计划之前，根据初步设计，对工程项目从开始建设（设计、施工准备）至竣工投产（动用）全过程的统一部署。工程项目总进度计划是根据初步设计中确定的建设工期和工艺流程，具体安排单位工程的开工日期和竣工日期。参见教材P6。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]