[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108383":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108383,783,1,"单选题","（）阐明各单位工程的建筑总规模及本年计划完成情况。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","年度计划项目表",false,{"key":16,"text":17,"correct":14},"B","投资计划年度分配表",{"key":19,"text":20,"correct":14},"C","工程项目总进度计划",{"key":22,"text":23,"correct":24},"D","年度竣工投产交付使用计划表",true,"考点:建设工程进度控制计划体系。年度竣工投产交付使用计划表将阐明各单位工程的建筑面积、投资额、新增固定资产、新增生产能力等建筑总规模及本年计划完成情况，并阐明其竣工日期。参见教材P8。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]