[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108382":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108382,783,1,"单选题","建设工程进度控制的总目标是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设工期",true,{"key":16,"text":17,"correct":18},"B","合同工期",false,{"key":20,"text":21,"correct":18},"C","定额工期",{"key":23,"text":24,"correct":18},"D","确保提前交付使用","考点:进度控制的概念。建设工程进度控制的最终目的是确保建设项目按预定的时间动用或提前交付使用，建设工程进度控制的总目标是建设工期。参见教材P1。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]