[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108381":3},{"question":4,"library":24},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":23},1108381,783,1,"单选题","下列建设工程进度控制措施中，属于合同措施的是（）。 A.建立进度协调会议制度 B.审查承包商提交的进度计划 C.对应急赶工给予优厚的赶工费 D.加强索赔管理，公正地处理索赔",[11,14,16,18,21],{"key":12,"text":12,"correct":13},"A",false,{"key":15,"text":15,"correct":13},"B",{"key":17,"text":17,"correct":13},"C",{"key":19,"text":19,"correct":20},"D",true,{"key":22,"text":22,"correct":13},"E","考点:进度控制的措施和主要任务。选项A属于组织措施；选项B属于技术措施；选项C属于经济措施。参见教材P3。",{"id":6,"name":25,"category":26,"favorite":27},"目标控制（土木建筑）","建筑工程",0]