[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108380":3},{"question":4,"library":24},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":23},1108380,783,1,"单选题","在建设工程监理工作中，不属于监理工程师控制进度的技术措施（）。 A.审查承包商提交的进度计划 B.编制进度控制工作细则 C.明确进度控制人员及其职责分工 D.结合电子计算机的应用，对建设工程进度实施动态控制",[11,14,16,19,21],{"key":12,"text":12,"correct":13},"A",false,{"key":15,"text":15,"correct":13},"B",{"key":17,"text":17,"correct":18},"C",true,{"key":20,"text":20,"correct":13},"D",{"key":22,"text":22,"correct":13},"E","考点:进度控制的措施和主要任务。技术措施主要包括：审查承包商提交的进度计划，使承包商能在合理的状态下施工；编制进度控制工作细则，指导监理人员实施进度控制；采用网络计划技术及其他科学适用的计划方法，并结合电子计算机的应用，对建设工程进度实施动态控制。选项C属于组织措施。参见教材P3。",{"id":6,"name":25,"category":26,"favorite":27},"目标控制（土木建筑）","建筑工程",0]