[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108379":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108379,783,1,"单选题","在施工进度控制目标体系中，关于建设工程施工进度目标分解图的说法中，不正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","需要明确项目建成交付使用的日期",false,{"key":16,"text":17,"correct":14},"B","需要明确单位工程交工动用的日期",{"key":19,"text":20,"correct":21},"C","上级目标受下级目标的制约",true,{"key":23,"text":24,"correct":14},"D","下级目标保证上级目标","考点:施工进度控制目标体系。在建设工程施工进度目标分解图中，建设工程不但要有项目建成交付使用的确切日期这个总目标，还要有各单位工程交工动用的分目标以及按承包单位、施工阶段和不同计划期划分的分目标。各目标之间相互联系，共同构成建设工程施工进度控制目标体系。其中，下级目标受上级目标的制约，下级目标保证上级目标，最终保证施工进度总目标的实现。参见教材P117。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]