[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108378":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108378,783,1,"单选题","将工程项目的施工进度控制目标按年度、季度、月（或旬）进行分解，并用实务工程量、货币工作量及形象进度表示，是按（ ）分解。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目组成",false,{"key":16,"text":17,"correct":18},"B","计划期",true,{"key":20,"text":21,"correct":14},"C","施工阶段",{"key":23,"text":24,"correct":14},"D","专业项目","考点:施工进度控制目标体系。按计划期分解，组织综合施工。将工程项目的施工进度控制目标按年度、季度、月（或旬）进行分解，并用实务工程量、货币工作量及形象进度表示，将更有利于监理工程师明确对各承包单位的进度要求。参见教材P118",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]