[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108377":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108377,783,1,"单选题","当工程项目有总承包单位时（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理工程师只需对总承包单位提交的施工总进度计划进行审核即可",true,{"key":16,"text":17,"correct":18},"B","对于单位工程施工进度计划，监理工程师不仅要负责编制还要负责审核",false,{"key":20,"text":21,"correct":18},"C","监理工程师要负责编制单位工程施工进度计划",{"key":23,"text":24,"correct":18},"D","工程项目由若干个承包单位平行承包时，监理工程师根本无必要编制施工总进度计划","考点:建设工程施工进度控制工作内容。当建设工程有总承包单位时，监理工程师只需对总承包单位提交的施工总进度计划进行审核即可。而对于单位工程施工进度计划，监理工程师只负责审核而不需要编制。参见教材P120",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]