[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108376":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108376,783,1,"单选题","建设工程施工进度控制工作从审核承包单位提交的施工进度计划开始，直至（ ）为止。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程竣工验收",false,{"key":16,"text":17,"correct":18},"B","工程保修期满",true,{"key":20,"text":21,"correct":14},"C","工程交付使用",{"key":23,"text":24,"correct":14},"D","工程款支付时","考点:建设工程施工进度控制工作内容。建设工程施工进度控制工作从审核承包单位提交的施工进度计划开始，直至建设工程保修期满为止。参见教材P120",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]