[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108374":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108374,783,1,"单选题","关于确定各单位工程的开竣工时间和相互搭接关系，下列说法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工顺序必须与主要生产系统投入生产的先后次序相吻合",false,{"key":16,"text":17,"correct":14},"B","应注意季节对施工顺序的影响",{"key":19,"text":20,"correct":14},"C","安排一部分附属工程或零星项目作为后备项目",{"key":22,"text":23,"correct":24},"D","注意主要工种和主要施工机械能间断施工",true,"考点:施工总进度计划的编制。注意主要工种和主要施工机械能连续施工。参见教材P125。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]