[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108372":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108372,783,1,"单选题","某工作是由三个性质相同的分项工程合并而成的，各分项工程的工程量和时间定额分别是：Q1＝3300m3，Q2＝3400m3，Q3＝2700m3；H1＝0.15工日／m3，H2＝0.20工日／m3，H3＝0.40工日／m3。则该工作的综合时间定额是（ ）工日／m3。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","0.29",false,{"key":16,"text":17,"correct":14},"B","0.28",{"key":19,"text":20,"correct":14},"C","0.25",{"key":22,"text":23,"correct":24},"D","0.24",true,"考点:单位工程施工进度计划的编制。计算劳动量和机械台班数。所有的工程量为：3300+3400+2700=9400m3，则该工作的综合时间定额为：（3300×0.15＋3400×0.20＋2700×0.40）÷9400＝0.24工日／m3。参见教材P127。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]