[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108369":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108369,783,1,"单选题","当工程延期事件发生后，承包单位应在合同规定的有效期内提交（ ），以便于监理工程师尽早了解所发生的事件。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","竣工验收报告",false,{"key":16,"text":17,"correct":14},"B","承包单位详情报告",{"key":19,"text":20,"correct":21},"C","工程延期意向通知",true,{"key":23,"text":24,"correct":14},"D","承包单位最终详情报告","考点:工程延期的申报与审批。当工程延期事件发生后，承包单位应在合同规定的有效期内以书面形式通知监理工程师（即工程延期意向通知），以便于监理工程师尽早了解所发生的事件，及时作出一些减少延期损失的决定。参见教材P133",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]