[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108363":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108363,783,1,"单选题","在施工过程中，遇到气候、水文、地质及周围环境等方面的不利因素，必然会影响到施工进度，属于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计变更的影响",false,{"key":16,"text":17,"correct":18},"B","施工条件的影响",true,{"key":20,"text":21,"correct":14},"C","各种风险因素的影响",{"key":23,"text":24,"correct":14},"D","物资供应进度的影响","考点:影响建设工程施工进度的因素。在施工过程中，遇到气候、水文、地质及周围环境等方面的不利因素，必然会影响到施工进度，属于施工条件的影响。参见教材P130。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]