[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108361":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108361,783,1,"单选题","物资供应进度控制的含义中，（ ）是将建设工程所需物资的供给纳入计划轨道，进行预测、预控，使整个供给有序地进行。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计划",true,{"key":16,"text":17,"correct":18},"B","组织",false,{"key":20,"text":21,"correct":18},"C","协调",{"key":23,"text":24,"correct":18},"D","控制","考点:物资供应进度控制概述。建设工程物资供应进度控制是指在一定的资源（人力、物力、财力）条件下，为实现工程项目一次性特定目标而对物资的需求进行计划、组织、协调和控制的过程。其中，计划是将建设工程所需物资的供给纳入计划轨道，进行预测、预控，使整个供给有序地进行。参见教材P136。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]