[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108358":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108358,783,1,"单选题","物资供应计划是用来指导和组织建设工程物资供应工作的计划，其编制依据主要包括货源资料和（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","物资加工计划.物资订货计划",false,{"key":16,"text":17,"correct":14},"B","物资采购计划.物资加工计划",{"key":19,"text":20,"correct":21},"C","物资需求计划.物资储备计划",true,{"key":23,"text":24,"correct":14},"D","物资申请计划.物资采购计划","考点:物资供应进度控制的工作内容。物资供应计划是反映物资的需要与供应的平衡，挖潜利库，安排供应的计划。它的编制依据是需求计划、储备计划和货源资料等。参见教材P140。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]