[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108355":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108355,783,1,"单选题","为了有效地控制建设工程施工进度，建立施工进度控制目标体系时应（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","首先确定短期目标，然后再逐步明确总目标",false,{"key":16,"text":17,"correct":14},"B","首先按施工阶段确定目标，然后综合考虑确定总目标",{"key":19,"text":20,"correct":14},"C","将施工进度总目标直接按计划期分解",{"key":22,"text":23,"correct":24},"D","将施工进度总目标从不同角度层层分解",true,"考点:施工进度控制目标体系。为了有效地控制施工进度，首先要将施工进度总目标从不同角度进行层层分解，形成施工进度控制目标体系，从而作为实施进度控制的依据。参见教材P117",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]