[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108354":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108354,783,1,"单选题","划分进度控制分界点，是将进度计划按照（ ）进行分解的。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目组成",false,{"key":16,"text":17,"correct":14},"B","计划期",{"key":19,"text":20,"correct":21},"C","施工阶段",true,{"key":23,"text":24,"correct":14},"D","专业项目","考点:施工进度控制目标体系。按施工阶段分解，划分进度控制分界点。根据工程项目的特点，应将其施工分成几个阶段，如土建工程科分为基础、结构和内外装修阶段。每一阶段的起止时间都要有明确的标志，特别是不同单位承包的不同施工段之间，更要明确划定时间分界点，以此作为形象进度的控制标志，从而使单位工程动用目标具体化。参见教材P118",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]