[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108353":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108353,783,1,"单选题","工程施工过程中为缩短工期而采取的措施中，属于组织措施的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","改进施工工艺和施工技术",false,{"key":16,"text":17,"correct":14},"B","实行包干奖励，提高奖金数额",{"key":19,"text":20,"correct":14},"C","采用更先进的施工机械",{"key":22,"text":23,"correct":24},"D","增加劳动力和施工机械的数量",true,"考点:施工进度计划的调整。组织措施：（1）增加工作面，组织更多的施工队伍；（2）增加每天的施工时间（如采用三班制等）；（3）增加劳动力和施工机械的数量。参见教材P132。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]