[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108352":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108352,783,1,"单选题","通过缩短某些工作的持续时间对施工进度计划进行调整的方法，其主要特点是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","增加网络计划中的关键线路",false,{"key":16,"text":17,"correct":18},"B","不改变工作之间的先后顺序关系",true,{"key":20,"text":21,"correct":14},"C","增加工作之间的时间间隔",{"key":23,"text":24,"correct":14},"D","不改变网络计划中的非关键线路","考点:施工进度计划的调整。施工进度计划的调整方法主要有两种，一是通过缩短某些工作的持续时间来缩短工期；一是通过改变某些工作间的逻辑关系来缩短工期。通过缩短某些工作的持续时间对施工进度计划进行调整时，其特点是不改变工作之间的先后顺序关系，通过缩短网络计划中关键线路上工作的持续时间来缩短工期。参见教材P132。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]