[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108351":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108351,783,1,"单选题","在施工进度计划实施过程中，为缩短工程总工期，可以采用的技术措施有（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","采用更先进的施工方法",true,{"key":16,"text":17,"correct":18},"B","改善外部配合条件",false,{"key":20,"text":21,"correct":18},"C","改善劳动条件",{"key":23,"text":24,"correct":18},"D","增加每天的施工时间","考点:施工进度计划的调整。具体技术措施包括：（1）改进施工工艺和施工技术，缩短工艺技术间歇时间；（2）采用更先进的施工方法，以减少施工过程的数量（如将现浇框架方案改为预制装配方案）；（3）采用更先进的施工机械。参见教材P132。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]