[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108350":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108350,783,1,"单选题","通过检查分析，如果进度偏差比较小，那么（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","仍按原计划执行",true,{"key":16,"text":17,"correct":18},"B","对原计划整体进行调整",false,{"key":20,"text":21,"correct":18},"C","改变工期或施工速度",{"key":23,"text":24,"correct":18},"D","应尽量减少变更计划性的调整","考点:施工进度的动态检查。通过检查分析，如果进度偏差比较小，应在分析其产生原因的基础上采取有效措施，解决矛盾，排除障碍，继续执行原进度计划。如果经过努力，确实不能按原计划实现时，再考虑对原计划进行必要的调整。即适当延长工期，或改变施工速度。计划的调整一般是不可避免的，但应当慎重，尽量减少变更计划性的调整。参见教材P132。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]