[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108349":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108349,783,1,"单选题","在建设工程施工阶段，监理工程师控制施工进度的工作内容是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","编制施工进度控制工作细则",true,{"key":16,"text":17,"correct":18},"B","编制施工准备工作计划",false,{"key":20,"text":21,"correct":18},"C","协助承包单位确定工程延期时间",{"key":23,"text":24,"correct":18},"D","及时支付工程进度款","考点:建设工程施工进度控制工作内容。建设工程施工进度控制工作内容主要有：（1）编制施工进度控制工作细则；（2）编制或审核施工进度计划；（3）按年、季、月编制工程综合计划；（4）下达工程开工令；（5）协助承包单位实施进度计划；（6）监督施工进度计划的实施；（7）组织现场协调会；（8）签发工程进度款支付凭证；（9）审批工程延期；（10）向业主提供进度报告；（11）督促承包单位整理技术资料；（12）签署工程竣工报验单，提交质量评估报告；（13）整理工程进度资料；（14）工程移交。参见教材P120。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]