[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108345":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108345,783,1,"单选题","下列情况，监理工程师有必要编制进度计划的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","单位工程施工的进度计划",false,{"key":16,"text":17,"correct":14},"B","大型建设项目的施工总进度计划",{"key":19,"text":20,"correct":21},"C","分期分批发包又没有负责全部工程的总承包单位的施工总进度计划",true,{"key":23,"text":24,"correct":14},"D","大型建设工程的工程项目进度计划","考点:建设工程施工进度控制工作内容。对于大型建设工程，由于单位工程较多、施工工期长，且采用分期分批发包又没有一个负责全部工程的总承包单位时，就需要监理工程师编制施工总进度计划；或者当建设工程由若干个承包单位平行承包时，监理工程师也有必要编制施工总进度计划。当建设工程有总承包单位时，监理工程师只需对总承包单位提交的施工总进度计划进行审核即可。参见教材P120",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]