[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108342":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108342,783,1,"单选题","当承包单位未能按合同规定的工期完成合同范围内的工作时对其的处罚是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","拒绝签署工程进度款支付凭证",false,{"key":16,"text":17,"correct":14},"B","中止施工承包合同",{"key":19,"text":20,"correct":14},"C","延长施工进度计划工期",{"key":22,"text":23,"correct":24},"D","误期损失赔偿",true,"考点:工程延误的处理。拒绝签署付款凭证一般是监理工程师在施工过程中制约承包单位延误工期的手段，而误期损失赔偿则是当承包单位未能按合同规定的工期完成合同范围内的工作时对其的处罚。参见教材P136",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]