[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108339":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108339,783,1,"单选题","某项工作的工程量为320m3，时间定额为0.5工日\u002Fm3，如果每天安排2个工作班次、每班8人去完成该工作，则其持续时间为（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","10",true,{"key":16,"text":17,"correct":18},"B","20",false,{"key":20,"text":21,"correct":18},"C","40",{"key":23,"text":24,"correct":18},"D","80","考点:单位工程施工进度计划的编制。工作的持续时间为：D=P\u002F（RB）=320×0.5\u002F（8×2）=10（天）。参见教材P128。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]