[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108337":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108337,783,1,"单选题","CM的基本指导思想是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","缩短了工程项目的建设工期，使部分工程分批投产，提前获得收益",true,{"key":16,"text":17,"correct":18},"B","调节计划进度与实际进度的改变",false,{"key":20,"text":21,"correct":18},"C","动态控制设计进度",{"key":23,"text":24,"correct":18},"D","加强与业主、监理单位、科研单位与承包商的协作与配合","考点:建筑工程管理方法。建筑工程管理（CM，Construction Management）方法是近年来在国外推行的一种系统工程管理方法，其特点是将工程设计分阶段进行，每阶段设计好之后就进行招标施工，并在全部工程竣工前，可将已完部分工程交付使用。这样，不仅可以缩短工程项目的建设工期，还可以使部分工程分批投产，以提前获得收益。参见教材P115。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]