[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108335":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108335,783,1,"单选题","建设工程物资需求计划的编制依据包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","物资运输计划",false,{"key":16,"text":17,"correct":14},"B","物资采购计划",{"key":19,"text":20,"correct":14},"C","物资的储备计划",{"key":22,"text":23,"correct":24},"D","施工图纸.预算文件.工程合同.项目总进度计划",true,"考点:物资供应进度控制的工作内容。它的编制依据主要有：施工图纸、预算文件、工程合同、项目总进度计划和各分包工程提交的材料需求计划等。参见教材P138。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]