[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108334":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108334,783,1,"单选题","建设工程材料的储备量，主要由材料的供应方式和现场条件决定，一般应保持（ ）天的用量。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","30",false,{"key":16,"text":17,"correct":18},"B","35",true,{"key":20,"text":21,"correct":14},"C","40",{"key":23,"text":24,"correct":14},"D","45","考点:物资供应进度控制的工作内容。建设工程材料的储备量，主要由材料的供应方式和现场条件决定，一般应保持35天的用量。参见教材P140。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]