[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108333":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108333,783,1,"单选题","关于物资需求计划的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","编制依据：概算文件.项目总进度计划",false,{"key":16,"text":17,"correct":18},"B","组成内容：一次性需求计划和各计划期需求计划",true,{"key":20,"text":21,"correct":14},"C","主要内容：确定材料的合理储备",{"key":23,"text":24,"correct":14},"D","编制单位：各施工承包单位","考点:物资供应进度控制的工作内容。物资需求计划一般包括一次性需求计划和各计划期需求计划。参见教材P138。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]