[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108330":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108330,783,1,"单选题","根据工程延期的审批程序，当延期事件具有持续性、承包单位在合同规定的有效期内不能提交最终详细的申述报告时，应先向监理工程师提交该延期事件的（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程延期估计值",false,{"key":16,"text":17,"correct":14},"B","延期意向通知",{"key":19,"text":20,"correct":21},"C","阶段性详情报告",true,{"key":23,"text":24,"correct":14},"D","临时延期申请书","考点:工程延期的申报与审批。当延期事件具有持续性，承包单位在合同规定的有效期内不能提交最终详细的申诉报告时，应先向监理工程师提交阶段性的详情报告。参见教材P133",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]