[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108329":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108329,783,1,"单选题","缩短某些工作的持续时间时，属于其他配套措施的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","实行包干奖励",false,{"key":16,"text":17,"correct":14},"B","增加工作面",{"key":19,"text":20,"correct":21},"C","改善外部配合条件",true,{"key":23,"text":24,"correct":14},"D","缩短工艺技术间歇时间","考点:施工进度计划的调整。其他配套措施包括：（1）改善外部配合条件；（2）改善劳动条件；（3）实施强有力的调度等。参见教材P132",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]