[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108328":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108328,783,1,"单选题","采用缩短某些工作持续时间的方法来调整施工进度计划的技术措施是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","实行强有力的调度",false,{"key":16,"text":17,"correct":14},"B","改善外部配合条件",{"key":19,"text":20,"correct":14},"C","增加每天的工作班次",{"key":22,"text":23,"correct":24},"D","采用更先进的施工机械",true,"考点:施工进度计划的调整。选项AB属于其他配套措施；选项C属于组织措施。只有选项D属于技术措施。参见教材P132",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]